  • Remove Safe-T-Strap™ from box.
  • Check Straps for unusual cuts or fraying. Ensure green protective sleeving is firmly  attached.
  • Once the shear wall is poured and the forms are being removed, place the looped end of the Safe-T-Strap™ over a developed re-bar dowel protruding through the top of the  shear wall.  Safe-T-Strap™s should be installed six (6) feet back from the  perimeter of the building.
  • Once Safe-T-Strap™ is installed, the forming of the floor continues and Safe-T-Strap™ is firmly  anchored by pouring concrete over the protective sleeve.
  • Once the fly forms or conventional forming is removed, Safe-T-Strap™ will be hanging from the  corner of the sheer wall and the ceiling - six feet back from the  perimeter.
  • Horizontal lifelines or static lines may be attached to two opposite embedded Safe-T-Strap™s. Two workers may then attatch their lifelines to the horizontal lifeline, providing maximum mobility and fall protection. Some  jurisdictions may require an engineer to certify a static line is acceptable for various work practices.
  • When the fall  hazard has been eliminated from the perimeter, i.e., the exterior wall has been  erected, the Safe-T-Strap™ is removed by cutting it off at the base.
  • Where shear walls or columns do not exist, Safe-T-Strap™s can be installed by inserting an 8" piece of rebar through the straps looped end, then inserting that end 4” into the poured concrete.